Timeline

2014

June: Offer on block

September: First contact with builder

November: PPA signed and deposit pad

2015:

March: notification titles delayed until June

May: Titles received, building contract received and prestart completed

June: Unconditional finance received & Settlement due

July:
– 1 July – File sent to construction
– 13 July – notification slab is booked for the week starting 20/7
– 17 July – Earthworks commenced
– 21 July – Footings
– 22 July – SLABBED

August:
– 6 August – Window frames delivered
– 7 August – Bricks delivered
– 11 August – Brickwork commenced!

September:
–Β 22 September – Plateheight reached

October:
– 7 October – Roof trusses delivered
– 9 October – Roof trusses installed
– 12 October – Scaffolding installed ready for upper slab pour
– 21 October – Upper slab pour
– 27 October – Upper floor framing commenced

November:
– 3 November – Upper floor framing, including wall frames, windows, eaves and fascia complete
– 10 November – EPS cladding / roof framing complete
– 13 November – Render complete
– 23 November – Upper floor painting commenced
– 25 November – Painting finished – roof sheets delivered

December:
– 1 December – Upper Floor colorbond commenced
– 9 December – Scaffold Drop
– 11 December – Lower floor framing commenced
– 14 December – Lower floor roof framing almost complete – fascias installed
– 17 December – Electrical run in

2016:

January:
– 15 January – Plumbing complete
– 18 January – Lower floor gutters installed and colorbond delivered
– 03 February – Lower roof install commenced
– 12 February – Roof apparently finished. It wasn’t. Grey float apparently complete – not started 😐 (30 weeks since slab down)
– 22 February – Grey Float finished
– 23 February – Ceiling installation commenced
– 25 February – Upstairs ceilings / walls finished. White Set commenced downstairs.

March:
– 8 March – Ceilings installed downstairs
– 10 March – Plaster commenced upstairs / downstairs ceilings finished
– 11 March – Upstairs cornices complete
– 12 March – Downstairs cornices 90% complete – ran out of cornice for the entry
– 18 March – Front render, Windows and doors fitted, stairs installed – lock up next week. (34 weeks from slab down)
– 24 March – LOCKED UP! (35 weeks from slab down)
– 30 March – Internal doors hung, all shelving installed (WIR’s, BIR’s, WIP, Linen Cupboard)

April:
– 6 April – Garage grano poured
– 8 April – Screed to wet areas (Week 37)
– 22 April – Tiling commenced
– 29 April – Cabinets Delivered

May:
– 2 May – Lower floor render painted and cabinets installed
– 6 May – Site clean
– 9 May – Garage door installed
– 11 May – Stone benchtops and sinks installed
– 18 May – Pavers delivered
– 20 May – Storm water piping prep, vinyl and mirror sliding doors installed
– 27 May – Kitchen cabinets finished – stone and sinks installed

June:
– 1 June – paving started
– 6 June – HWS & toilets installed – Paving complete
– 9 June – Tiler back for finals. Electrical finals underway
– 10 June – electrical finals and gloss paint 90% finished

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s